Field Installation Teams
Total Field Teams
8
All active on site
Total Technicians
24
App-enabled GPS
Today Installations
42
Across 3 projects
Average Daily Run-rate
5.2
Poles/team per day
Team Alpha
On Duty
#PRJ-2026-001
Linked Project: Lucknow Municipal Street Lighting
Team Leader: Ramesh Verma
+91 98711 00223
Members: Anil Sharma, Dinesh Kumar
Zone: Gomti Nagar Ext. (Poles 001–150)
Completion: 140 / 150 Units
93%
Team Beta
On Duty
#PRJ-2026-001
Linked Project: Lucknow Municipal Street Lighting
Team Leader: Praveen Sharma
+91 98110 33445
Members: Sunil Verma, Ashok Yadav
Zone: Hazratganj VIP (Poles 151–300)
Completion: 100 / 150 Units
67%
Team Gamma
On Duty
#PRJ-2026-002
Linked Project: Bhopal Smart City High Mast Solar
Team Leader: Suresh Patel
+91 98220 55667
Members: Kailash Sen, Deepak Sahu
Zone: Lake View & MP Nagar Hubs
Completion: 48 / 80 Units
60%
Team Delta
On Duty
#PRJ-2026-003
Linked Project: Basti Govt. School Rooftop Solar
Team Leader: Vikram Singh
+91 94150 77889
Members: Santosh Dubey, Manoj Pandey
Zone: Harraiya & Vikramjot Blocks
Completion: 95 / 120 Units
79%